Overview
Land Area : 612㎡
Construction Area : 366㎡ (Building-to-land ratio 59.9%)
Total Floor Space : 1,154㎡(Floor-area-to-site 188%)
Size : 5 stories (B1 ~ 4F) / 11 parking spaces
Units : 26
Construction Period : Mar 5, 2018 ~ Dec 29, 2018
Progress
Plan Approved: August 2017
Design Completed: July 2017
Construction Started: March 2018
Completion : December 2018